The master schedule tells you when the building finishes. The three-week look-ahead tells your subs what to show up for on Monday. For small and mid-size general contractors, the look-ahead is the schedule that actually runs the job. Here is how to build one that people follow.
The short version
- Break master schedule activities into area-by-area, company-by-company bars.
- Put a company on every bar and link what waits on what.
- Get each sub to confirm their dates, and chase late work right away.
What a look-ahead is (and isn't)
A look-ahead covers the next two to four weeks in more detail than the master schedule: activities by area, by company, by day. It isn't a second CPM schedule. It's a working plan you update every week, usually in the weekly sub meeting.
Building one in five steps
- Pull the next three weeks from the master schedule. Start with the big activities that fall in the window.
- Break them down by area and trade. "Drywall" becomes "Hang Level 2 east," "Hang Level 2 west," "Tape Level 1."
- Put a company on every bar. A bar without a company is a bar nobody owns.
- Link what waits on what. Tape can't start until hang is done in that area, and inspections sit between them. When one slips, you see what moves with it.
- List the constraints. Submittals not approved, material not delivered, RFIs not answered. A bar with an open constraint isn't ready to start.
Getting subs to commit
A look-ahead only works if the foremen agree to it. Send each company its own activities and ask them to confirm. If they can't make a date, you want to hear it this week, not when the crew doesn't show.
Chasing late work
When an activity runs past its finish, ask the sub right away: is it done, or do you need more time? If they need more time, get a new date and a reason, then decide whether to accept it. Do it consistently and the look-ahead stays honest.
Weekly look-ahead routine
- Pull the next three weeks from the master schedule
- Break activities down by area and trade
- Put a company on every bar
- Link predecessors
- List open constraints (submittals, deliveries, RFIs)
- Send each company its own activities
- Get each foreman to confirm
- Ask about every bar past its finish
- Accept or decline new dates with a reason
Try it in ProjectAire
ProjectAire's look-ahead schedule has bars by company, multiple predecessors with lag, and a work calendar. It also chases late work on its own: when a bar runs past its finish, the sub's schedule contact gets a link (no login) to say "it's done" or request an extension with a new date. You approve or decline the extension, and everything that depends on it moves. You can try the schedule demo first.