Three-week look-ahead schedule: a how-to for small general contractors

Build a three-week look-ahead schedule your subs follow: break down activities, put a company on every bar, link dependencies and chase late work.

In this post
  1. What a look-ahead is (and isn't)
  2. Building one in five steps
  3. Getting subs to commit
  4. Chasing late work

The master schedule tells you when the building finishes. The three-week look-ahead tells your subs what to show up for on Monday. For small and mid-size general contractors, the look-ahead is the schedule that actually runs the job. Here is how to build one that people follow.

The short version

  • Break master schedule activities into area-by-area, company-by-company bars.
  • Put a company on every bar and link what waits on what.
  • Get each sub to confirm their dates, and chase late work right away.

What a look-ahead is (and isn't)

A look-ahead covers the next two to four weeks in more detail than the master schedule: activities by area, by company, by day. It isn't a second CPM schedule. It's a working plan you update every week, usually in the weekly sub meeting.

Building one in five steps

  1. Pull the next three weeks from the master schedule. Start with the big activities that fall in the window.
  2. Break them down by area and trade. "Drywall" becomes "Hang Level 2 east," "Hang Level 2 west," "Tape Level 1."
  3. Put a company on every bar. A bar without a company is a bar nobody owns.
  4. Link what waits on what. Tape can't start until hang is done in that area, and inspections sit between them. When one slips, you see what moves with it.
  5. List the constraints. Submittals not approved, material not delivered, RFIs not answered. A bar with an open constraint isn't ready to start.

Getting subs to commit

A look-ahead only works if the foremen agree to it. Send each company its own activities and ask them to confirm. If they can't make a date, you want to hear it this week, not when the crew doesn't show.

Chasing late work

When an activity runs past its finish, ask the sub right away: is it done, or do you need more time? If they need more time, get a new date and a reason, then decide whether to accept it. Do it consistently and the look-ahead stays honest.

Weekly look-ahead routine

  • Pull the next three weeks from the master schedule
  • Break activities down by area and trade
  • Put a company on every bar
  • Link predecessors
  • List open constraints (submittals, deliveries, RFIs)
  • Send each company its own activities
  • Get each foreman to confirm
  • Ask about every bar past its finish
  • Accept or decline new dates with a reason

Try it in ProjectAire

ProjectAire's look-ahead schedule has bars by company, multiple predecessors with lag, and a work calendar. It also chases late work on its own: when a bar runs past its finish, the sub's schedule contact gets a link (no login) to say "it's done" or request an extension with a new date. You approve or decline the extension, and everything that depends on it moves. You can try the schedule demo first.